The Project: Mud Walls Secondary Road reinstatement
Client: DIER
Value: $4.6M
Construction Period: Feb 2012 - Mar 2013
Location: Mud Walls Road, North of Colebrook
Superintendent's Representative: Gunadasa Ginneliya
Stakeholder Engagement:
- Telstra
- Local farmers
- Local residents
- Heritage Tasmania
Project Manager: Stewart Geeves / Brendan Moore
Project Foreman: Geoff McKenna / Jade Clark
Scope of Works
Widening and pavement repairs to 7km of Mud Walls Road, north of Lovely Banks junction. 4km of pavement and drainage repairs south of Lovely Banks Junction.
The project included:
- Earthworks
- Surface and subsoil drainage
- Stormwater works
- Supply and placement of base and sub base
- Installation of traffic facilities
- Environmental and heritage management
- Utility relocation
- Traffic management
- Reclaim existing pavement
- Removal of 300 trees