The Project: Major road upgrade and rehabilitation
Client: Department of State Growth
Value: $7.5M
Construction Period: Two construction seasons from October through to March 2017-2018 and 2018-2019
Location: Highland Lakes Road, Liawenee
Project Manager: Adam McKeown
Project Foreman: Jade Clark
Superintendent's Representative: Robyn Hawkins
Scope of Works
Upgrade of 12.5km of unsealed road to sealed with stabilisation and overlay, including upgrade of select drainage works.
The project included:
- 2 per cent lime stabilisation of existing gravel road
- 100mm to150mm overlay with Class 2 material
- Clearing of drains
- Culvert upgrades/extensions
- Sealing
- Line marking